ServicesCivils and groundworks
Civil engineering and groundworks
Coordinate enabling, foundations, below-ground services and external works around the design, programme and retained site access. Survey existing conditions, confirm receiving levels and agree the statutory and client interfaces before works commence.

Survey the site, prove what is below ground and plan what comes next
We coordinate enabling works, earthworks, foundations, drainage, utilities and external works around the condition and use of the site. The first decisions are access, levels, temporary works and what needs to be verified below ground before excavation and permanent work.
Confirm the constraints
Review utility information, surveys, ground conditions and nearby structures. Agree where verification, trial holes or further specialist investigation are required.
Plan the sequence
Coordinate excavation, temporary access, protection to retained services, formation levels and when underground connections can be made.
Record before covering
Confirm the inspection and testing requirements for foundations, drainage and utilities. Record levels and locations before backfill, then agree the handover evidence.
Scope, interfaces and acceptance
Design coordination and installation
Plan temporary access, formation and service continuity per phase. Review excavation provisions and designed temporary works with the responsible team before work. Set out inspection stages for foundations, services and drainage before backfill.
Inspection, testing and handover
Agree inspections, as-built levels and routes, test records and any adoption or reinstatement responsibilities before work begins.
Related packages

Civil engineering and groundworks packages
C01 · Earthworks

Review ground investigation, existing services and materials classification. Confirm excavation extent, formation, imported materials, disposal and protection of surrounding access.
Handover. Record formation inspections, disposal evidence as applicable, levels and acceptance of fill.
C02 · Foundations

Work to the project structural design and ground investigation. Coordinate setting out, obstructions, service crossings, excavation provisions, inspections and concrete or piling sequence.
Handover. Capture dimensions, levels, reinforcement or piling records and tests required by the engineer.
C03 · Drainage and sewers

Set foul and surface-water routes, gradients, invert levels, receiving connections and inspection access. Establish temporary flow, consents and any sustainable drainage requirements.
Handover. Deliver the specified drainage tests, surveys and checked as-built levels and connection records.
C04 · Highways and infrastructure

Coordinate construction and inspection stages with the relevant authorities and project requirements. Agree live traffic and pedestrian access, retained routes and staged reinstatement.
Handover. Record materials, formation, levels, tests and agreed reinstatement or adoption documentation.
C05 · Utilities

Confirm existing service records, verified positions and the scope of new or diverted utilities. Agree permits and service continuity and coordinate ducts, chambers and owner interfaces.
Handover. Record routes, depths and levels as agreed and hand over tests and provider records where specified.
C06 · Structural works

Coordinate concrete and steelwork, setting out, connections and tolerances with the designer. Plan lifting and temporary stability and confirm inspection and closure points.
Handover. Record inspections, material certification and verification required by the specification.
C07 · External works

Agree levels, drainage falls, accessibility, paving, kerbs and landscape details alongside utility access. Set temporary routes and protection through sequence changes.
Handover. Check layout, levels, falls, finishes and care or maintenance information.
C08 · Site infrastructure

Plan compounds, haul roads, welfare and temporary access against delivery and emergency requirements. Agree who designs, implements and inspects temporary works as the site evolves.
Handover. Set out current logistics drawings, inspection and handover points and the agreed removal and reinstatement sequence.